Specialized brigades from the Villa Clara Electric Company are working on the repair of the fault - Image © Facebook/Empresa Eléctrica Villa Clara

A significant malfunction at the Gran Panel substation in Santa Clara remains unresolved, despite the Electric Union's (UNE) earlier promise that service would be gradually restored on Monday night and early Tuesday morning.

In their recent update, the state-owned company indicated that specialized teams from Villa Clara are still at work on the installation to fix the issue, which is impacting circuits 166, 167, 168, 169, 28, 170, and 171. These circuits encompass areas such as Condado, Virginia, and the José Martí district.

The UNE has not specified how many of these circuits are still without power nor provided a new timeline for completing the repairs. Some circuits reportedly had service restored on Monday, so it cannot be said all users were without electricity continuously, though a substantial number of households remain affected.

Previously, Carlos Benavides Navarro, the director of the Villa Clara Electric Company, explained that the repair work involves replacing heavy conductors, which are difficult to handle, located between a main transformer device and the substation's power bar.

The official stated that the necessary resources for the repair were available, but its complexity necessitated specialized teams. However, authorities have not clarified what caused the damage to the conductors or detailed the extent of the substation's damage.

The breakdown was reported on Monday, though the exact time of occurrence has not been publicly disclosed.

This outage exacerbates the power supply issues faced by many Santa Clara residents, who are already dealing with extended blackouts due to the National Electric System's (SEN) generation shortfall.

This is not the first major disruption Santa Clara has experienced in recent weeks. On October 29, a fault in a 110-kilovolt high-voltage line left much of the city without electricity. At that time, authorities attributed the issue to the line tripping, but no connection with the current malfunction has been established.

The Gran Panel substation itself was the site of a fire in April 2020, which damaged interior cabinets used to operate various distribution circuits. Authorities reported then that the main transformer was not affected.

Understanding Santa Clara's Power Outages

What caused the current power outage in Santa Clara?

The exact cause of the conductor damage leading to the current outage has not been disclosed by the authorities.

Has Santa Clara experienced similar issues recently?

Yes, on October 29, a fault in a high-voltage line caused significant power outages in the city.

What steps are being taken to resolve the outage?

Specialized teams from Villa Clara are working on replacing heavy conductors to resolve the issue.