Extended Hours at Guiteras Power Plant as Pipe System Remains Offline

Monday, November 16, 2026 by Zoe Salinas

Extended Hours at Guiteras Power Plant as Pipe System Remains Offline
Maintenance of the Guiteras - Image © Facebook / CTE Guiteras

The Antonio Guiteras Thermoelectric Power Plant, Cuba's largest electricity generator, remained offline this Sunday. Welding teams are tirelessly working to restore the pipe system crucial for the plant's reactivation.

According to the plant's official Facebook page, efforts are being made around the clock to repair the raw water intake pipes, described as a "vital task for the unit's startup and return to service."

The plant exited the National Electric System on Wednesday, November 11—marking its 28th shutdown in 2026—while generating around 180 MW, due to a leak in the boiler's economizer. Subsequent inspections uncovered damage to the economizer, high-temperature reheater, and the nurse tank area.

Engineer Elmer García Romero, the block's technical deputy director, confirmed to Radio 26 that alongside fixing the economizer, the plant's most damaged component, around 180 corrective tasks are underway, supported by the Central Repair Unit and maintenance crews from western power plants.

Welding teams from ESTEC and the plant itself have been working nonstop, including night shifts. Images from the facility show numerous workers in protective gear laboring under construction lights in the early morning hours.

José Miguel Solís, a journalist from Matanzas who specializes in tracking the plant, predicted on Friday, November 13 that the plant might begin operations early Monday, November 16. However, as of the end of Sunday, work on the raw water pipe system was ongoing, and the unit remained classified as out of service due to failure.

The situation worsens an already critical power crisis. On Sunday, the Electric Union projected only 970 MW available against a demand of 2,800 MW, leading to a deficit of 1,830 MW and power outages lasting up to 20 hours daily in many provinces.

In addition to Guiteras, other major plants are also offline: the Ernesto Guevara Power Plant lost its last active unit on Friday, November 13, leaving its three blocks—collectively capable of 295 MW—completely non-operational. Meanwhile, the Felton Power Plant in Holguín has not generated any electricity for weeks.

Guiteras has been operational for nearly 38 years and has not undergone a full overhaul for about 16 years, explaining its frequent breakdowns. Rubén Campos Olmos, the general director of the Electric Union, estimated in June 2026 that a comprehensive repair would require intervention on over 500 pipes, executing between 1,000 and 1,200 welds, and keeping the unit offline for about six months—a duration the National Electric System cannot accommodate without sufficient backup generation.

As welders continue their nighttime efforts, November 16 remains the target date for Guiteras to rejoin the system, although the plant itself has not confirmed a specific startup time.

FAQs on the Guiteras Power Plant Shutdown

Why is the Guiteras Power Plant offline?

The plant is offline due to a leak in the boiler's economizer, which is part of a larger set of damages affecting the plant's operation.

What are the current power demands in Cuba?

As of the latest projections, there is a demand of 2,800 MW, with only 970 MW available, resulting in significant power shortages.

When is the Guiteras expected to resume operations?

The plant is tentatively scheduled to resume operations on November 16, though no specific time has been confirmed.